Home > Catalogue > Collective Procrastination
Also Known As:
The team needs to handle several commitments in parallel, so it focuses on most pressing issues (from other commitments) until the iteration commitment becomes pressing, then rushes to finish off the iteration. The bad consequence is that from the outside, actual status of work done is not known during the iteration which hinders planning and problem solving.
(Alternative cause with the same symptoms and consequences: Team wants reduce the administrative overhead of reporting time spent on tasks, so it delays reporting until it becomes a pressing issue. Additional bad consequence is that from the inside, the data reported does not correctly reflect reality.)
The stalled progress is until 10th April, the rock edge of the burndown occurs on 10-13th April.
|Anti-pattern | Relation | |–|–| | Fire Drill | specific cause of management spending to much time on pre-development activities |